We have already marginally
dealt with local sources in our article Legislative “whirlwind” brings
significant changes and new opportunities in the Slovak energetics, which
was published in the issue No. 1/2019 PRO-ENERGY Magazine. The article concerned the amendment to
the Renewable Energy Support Act, which brought the biggest changes of the last
decade in the Slovak energetics. Its major changes included also the
implementation of a new institute – local source.
Firstly, it is necessary
to mention that the main impulse for the implementation of the local source
into our legal code came from the part of the Slovak association of
photovoltaic industry and Renewable energy sources (SAPI). After all, the
concept of the local source itself comes from the Association as well.
The main reasons
motivating the creation of a new type of source in our legislation can be seen
mainly in the effort to break the so-called “stop state.” The stop state has
been in existence since the year 2013 throughout all regional networks.
While the “stop state” had
no support of the law, because of it, it was factually impossible to connect
any unit for the production of electricity with the installed capacity higher
than 10 kW into a distribution network. Due to the impossibility to install new
sources, the energetics within RES was basically sleeping until the year 2019.
Of course, another
motivation for the implementation of the local source was the fulfilment of the
commitments of Slovakia towards the European Union, mainly regarding the
proportion of electricity produced from renewable energy sources. However, the
demand of many subjects for the installation of energetic units, which would
bring them energy costs savings, cannot be overlooked either.
After its successful
incorporation into our legislation (with the effectiveness from 1st January
2019), the local source has been in Slovak energetics for almost two years. The
success is that it, at least partly, helped to break the still lasting factual
“stop state.” However, the possibility of its connection to the network is
still dependent on the disposable (free) installed capacity, which the Ministry
of Economy of the Slovak Republic determines annually (the Ministry).
However, it is
questionable if the local source has been able to fully utilize its potential
since its implementation. Hence, after the introduction of its basic
characteristics, we will look closer in this article at its utilization in
practice and at some application problems with the connection to the network,
which we have so far encountered in our law firm.
Regarding the
characteristics of the local source itself, it is a source, which, according to
the law, is intended to be used exclusively for the production of
electricity for own consumption.
Another condition is that
the local source must produce energy only from renewable energy sources, such
as water, wind, sun, biomass, biogas, geothermal energy, etc. Further, the law
limits the maximum installed capacity of the local source to 500 kW.
As it is a source intended
solely for the production of electricity for own consumption of the offtake point,
the legislator imposed another restriction concerning its total installed
capacity. It cannot be higher than the maximum reserved capacity of the offtake
point. The aim of the restriction is so that the producer does not produce more
energy than it is able to consume on their own.
The law also allows the local
source certain flows of electricity into the network. For this reason, the
maximum reserved capacity of the local source is no more than 10% of the total
installed capacity of the local source. However, the regime of the allowed
flows is set differently for entrepreneurs and non-entrepreneurs. Furthermore,
with regard to entrepreneurs (producers with a license in energetics), the law
allows the producers to sell the excess electricity to the consumers on the
market. However, such supply still cannot exceed the maximum reserved capacity
of the local source. In case of exceeding the allowed flows, it would constitute
an unlawful supply of electricity on the part of the producer and the risk of
their physical disconnection from the network.
Except for the advantages
in the form of the right to free and preferential connection to the
distribution network, as well as the free replacement of the designated meter,
it is worth mentioning that the producer in the local source is exempted from
paying the tariff for the operation of the system for all produced electricity,
which he consumes on his own.
In relation to these
advantages, it is necessary to point out that the electricity produced in the local
source is not supported by a surcharge or the purchase of electricity for a
regulated price.
As we have already
mentioned, the local sources cannot be connected unlimitedly. The capacities
available for connection are set annually by the Ministry. In practice, the
available capacities, which can be connected to the network, are divided between
the three operators of the regional distribution network in the notice of the
Ministry.
Table No. 1 shows the
overview of the allocated available capacities according to the individual
regional distribution companies.
|
2019 |
2020 |
2021 |
Západoslovenská distribučná a.s. (hereinafter referred to as „ZSD“) |
13 MW |
8 MW |
5 MW |
Stredoslovenská distribučná
a.s. |
10 MW |
6 MW |
15 MW |
Východoslovenská distribučná
a.s. |
8 MW |
5 MW |
16 MW |
For completeness, we state
that the system of drawing of the available capacities is set in a way that if the
whole capacity is not used within a particular year, it is possible to relocate
it and use it in the next period.
In relation to this, the
regional distribution companies at their official websites continuously publish
the actual state of drawing of the available capacities.
ZSD |
16,984
MW |
SSD |
9,21004
MW |
VSD |
2,978
MW |
As can be seen from the
table above, more than half of the 50 MW capacity allocated for the years 2019
to 2020 was still available to the date of 18 August 2020. Therefore, the
question arises whether there is such a low demand for the local sources on the
market or there is another reason for such low drawing of available capacities.
According to the
information available to us, producers are interested in the local sources. For
instance, according to the data published at its website, VSD already registers
250 applications for the installation of the local source. However, a large
number of applications for the installation of the local sources are rejected by
the distribution company. A similar situation is also within the two remaining
regional distributors. However, we do not know the exact reasons for the rejection
of the applications of individual producers. The distribution companies do not
publish the reasons on their websites.
Nevertheless, we regularly
encounter one specific reason for the rejection of applications for the
connection of local source for the applicants, at which local source has the biggest
prospect.
In our practice, we
noticed that there is quite a large interest in connecting local sources to
local distribution networks (MDS).
However, numerous clients
met with the resistance of the regional distributors in this matter, which
constantly reject the connection of local sources to the local distribution
networks.
We met with such a negative
approach to the connection of local source to the local distribution network for
the first time last year during the then-ongoing energetic conference, where
such opinion was expressed by a representative of one of the regional
distributors.
As it became clear after
some time, this opinion is shared by all three operators of the regional
distribution networks. According to the distribution companies, the available
capacities for the connection of new local sources apply solely to the units
connected to the regional distribution networks. However, from our point of
view, this opinion cannot be agreed with.
Said discussion regarding
the possibility of connecting local source to the local distribution network
arose within the interpretation of the provision of Section 14 (1) (e) of the Renewable
Energy Support Act. The provision in question regulates the competency of the
Ministry to determine the available capacities for the connection of the local
source to the network.
However, said legal
provision does not differentiate between the types of the distribution network
to which the new unit for the production of electricity can be connected. In
the provision, the Act uses only the general word “network,” and does that without
differentiating whether it is a local or a regional distribution network.
Respecting the legislation, we are of the opinion that the refusal to connect the
local sources to the local distribution network is unacceptable. The said
objection applies even more since the individual operational rules subordinate
the installation of any sources into the local distribution network to the
approval of the regional distributors. If we went to the extreme, following the
opinion of the distribution companies, it would not be possible to install
anything whatsoever into the local distribution network. To the local
distribution network, the established stop state, which the amendment to the Renewable
Energy Support Act sources sought to break, would still apply in its entirety.
Moreover, we are of the
opinion that such allocation of the capacity, exclusively for the benefit of
the regional distribution network would clearly be inconsistent with Section 3
(1) of the Regulation Act, according to which the “aim of the regulation is to
ensure the availability of the commodities and relating regulated activities in
a transparent and non-discriminatory way (…).” Thus, it is clear that within
the legal regulation, there are certain quality requirements of a fair and
transparent ensuring of the availability of the commodities and relating
regulated activities, that is, the prohibition of discrimination is also
emphasized.
Therefore, we think that
the notice of the disposable installed capacities for the new sources must be
interpreted in a way that the Ministry of Economy of the Slovak Republic
determined the installed capacity for the regional distribution networks,
including the subordinate networks connected to them. A different
interpretation would be, from our point of view, discriminatory at the least to
the potential producers, who are connected to the local distribution networks.
We assume that if the
regional distributors do not change their opinion, it is possible that some of
the rejected applicants will protect their rights in a court.
The implementation of the local
source brought at least small recovery to the energetic market after long years
of the blanket “stop state.”
Nonetheless, as it seems
from the published data, the local source has not been fully utilizing its
potential so far. It is possible to argue about the reasons, but from our
practice, we know that the strict approach of the regional distribution
companies, which without legal justification obstruct the drawing of the
available capacities in case of projects, which are to be carried out in local
distribution networks, plays a part in this.
However, we believe that
the situation will change soon, and it will be possible to connect the local
sources to the local distribution networks. We expect the impulse towards this
change due to the commitments of the Slovak Republic, which are set in the
National energy and climate plan for the years 2021 – 2030. The plan includes
the commitment to reach the proportion of energy from renewable energy sources in
the gross final energy consumption to be 19,2% in the year 2030.
Fulfilment of these
ambitious goals with the help of the local sources (at least partially) could
be the right way. A positive effect on the fulfilment of these goals is
multiplied by the fact that due to the absence of any type of support, local
sources do not increase the final price of the electricity for the
consumers.