Regarding the installation of a local source into the
network, there have been numerous controversies and uncertainties in the legal
practice. Recently, the most resonant has been the question whether it is
possible to connect a new local source only to the regional distribution
network or also to the local distribution network (LDN). On our part, we became aware of said question in
October 2019, during the then ongoing ENERGOFORUM conference. During the
conference, one of the regional distributors objected against the
possibility of connecting the local source into the LDN, which was
presented in the panel discussion by our colleague, Juraj Ondrejka. The opinion
of the regional distributor was, surprisingly, supported also by the
representative of the Ministry of Economy of the Slovak Republic.
Before closely explaining the above-mentioned
question, we consider it to be necessary to state the legal definition of a
legal source. That is defined in the Act on Support of Renewable Energy Sources
as follows: “a local source is a unit for production of electricity from a
renewable source of energy, which produces electricity for the coverage of the
consumption of the supply point identical to the delivery point of this unit
for the production of electricity, and the total installed capacity of which is
to 500 kW including, but no more than the amount of maximum reserved capacity
of such supply point.
The „Blanket stop state” applies
As it is generally known, the regional distribution
companies have since the end of the year 2013 factually stopped the receipt of
new applications for the connection of a unit for the production of electricity
to the distribution network (the so-called blanket stop state).
The above-mentioned “stop state”, however, according
to the notices of the regional distribution companies (referring to the
provision of Sec. 3 (1) (c) of the Act on Energy) does not apply to the
applications for the connection regarding the local sources, which are not
obliged to pay the tariff for the operation of the system. According to the
notice of the Ministry of Economy of the Slovak Republic, the disponible installed
capacity determined for the connection of new local sources for the year 2020
was 19 MW. According to the opinion of the regional distributor, presented at
the conference, the disponible capacities for the connection of new sources
only apply to the units connected to the regional distribution network.
However, we are of the opinion that it is not possible
to agree with this opinion. The competence of the Ministry of Economy of the
Slovak Republic to determine the disponible capacities is provided in the
provision of Sec. 14 (1) (e) of the Act on Support of Renewable Energy Sources.
Said legal provision, however, does not differentiate between the types of
the distribution networks to which the new source for the production of
electricity can be connected. In this provision, the act only uses the
general word “network” without differentiating whether it is a local
distribution network or a regional distribution network.
The refusal to connect the sources is unacceptable
Regarding the legislation, we are of the opinion that
the refusal to connect the local sources to the LDN is unacceptable. Said
objection applies even more due to the fact that the individual operational
rules subordinate the installation of any sources into the LDN to the
approval of the regional distributors. If we went to the extreme, according
to the opinion of the regional distributor, it would not be possible to install
anything whatsoever into the LDN.
From our point of view, this interpretation of the
regional distributor would cause an undesirable state, in which within the
development projects in the LDN, it would not be possible to connect any source
into the subordinate network. To the LDN, the established stop state, which
the legislation on the local sources sought to bypass, would still apply in
its entirety.
Further, we are of the opinion that such allotment
of the capacity, exclusively for the benefit of the regional
distribution network would clearly be inconsistent with Sec. 3 (1) of the Act
on Regulation, according to which the “aim of the regulation is to ensure
the availability of the commodities and relating regulated activities in a
transparent and nondiscriminatory way (…).”
From the cited provision, it is clear that within the
legal regulation, there are certain quality requirements of a fair and
transparent ensuring of the availability of the commodities and relating
regulated activities, that is, the prohibition of discrimination is also
emphasized.
What is our opinion?
Therefore, we think that the notice of the disponible
installed capacities for the new sources must be interpreted in a way that the Ministry
of Economy of the Slovak Republic determined the installed capacity for the
regional distribution networks, including the subordinate networks connected to
them. A different interpretation would be, from our point of view, discriminatory
at the least to the potential producers, who are connected to the local
distribution networks.
The question is how the regional distributors will
deal with the potential objections against the breach of the prohibition of
discrimination, which they are likely to face from the part of the applicants
for the connection of the local sources into the LDN.
We assume that if the regional distributors do not
change their opinion, it is possible that some of the refused applicants
will protect their rights through a court action.