Cookie Consent by Free Privacy Policy Generator

2 MARCH 2021

The requirements for construction of renewable energy sources in Slovakia. What processes must the investors go through?

 

Author of the article

Juraj Ondrejka

PARTNER

Andrea Puková

ASSOCIATE

The issue of building and connecting a new renewable energy source (RES) is currently a source of disappointment for many green energy producers. The actual construction of the source is of course feasible on a theoretical level, but the problem arises if the potential producer finds that he will not be able to connect it to the distribution system. Since 2013, the regional distribution companies have taken the same view that there is simply no capacity in the system to connect any new sources. Not even to local distribution systems (LDS). Building a renewable energy source with an output of more than 10 kW in Slovakia has been an almost impossible task since 2013. Even if some lucky producer succeeds, it is more of an exception to the rule. 

NEW OPPORTUNITIES IN ENERGY SECTOR

The long-awaited (and highly demanded) change occurred in 2019, when a major amendment to the RES Support Act entered into force. In addition to other significant changes, it also brought a partial breaking of the stop state. We have already dealt with this amendment in our article Legislative "whirlwind" brings significant changes and new opportunities in the Slovak energetics, which was published in issue 1/2019.

The amendment tried to break the stop state in several ways.

In the first place, it established that the Ministry Economy of the Slovak Republic (hereinafter referred to as the Ministry) annually by 30 June publishes on its website the installed capacity of new plants for the production of electricity from RES and CHE (cogeneration of heat and electricity) supported by a surcharge, that can be connected to the system.
Secondly, a new type of support was added to the support act - a supplement. It shall be provided to plants with a total installed capacity of 10 kW to 50 MW. It is determined as the difference between the offered price of electricity and the price of purchased electricity, which is calculated by the Regulatory Office for Network Industries (RONI). It is to be paid for a period of 15 years.

Despite these efforts, however, obstacles have arisen in practice, which make connecting new sources still a difficult task. 

PLANTS ON SURCHARGE

As we have mentioned, the first opportunity was the possibility of connecting the new sources on surcharge, according to the available capacities for the connection, published on an annual basis by the Ministry.

Despite the fact that the Ministry does not idle and since 2019 (including the capacity for the year 2021) it has “enabled” to connect a total of 39 MW RES plants and 21 MW CHE plants within the whole of Slovakia, the connection possibilities are still limited. Support in the form of surcharge is provided under very limited circumstances and for relatively small outputs. For example, you will only receive a surcharge for RES for plants using hydropower, geothermal energy, biogas, landfill gas or sewage treatment plant gas, while the total installed capacity of this source cannot exceed 500 kW. CHE sources will receive a surcharge only if they have a total installed capacity of up to 1 MW, use at least 60% of the heat produced to supply heat to the central heat supply system and achieve at least 10% primary energy savings.

At the same time, as the Ministry determines the available capacity for the three regional distribution system operators, they make no secret of the view that new sources for surcharge can only be connected to regional distribution systems. Connecting sources for surcharge to the LDS can be problematic at the very least.

SUPPLEMENT AND AUCTIONS

Regarding the supplement, it is still awaiting the first producer. The reason is simple - obtaining the right to support in the form of a supplement is possible only on the basis of success in the tender, the so-called auctions. These auctions are to be organized by the Ministry.

At the beginning of the year, the Ministry actually initiated such an auction. In February 2020, it published a call on its website to submit bids for an auction, in which it planned to "distribute" 30 MW of installed capacity. The auction was announced for the following new sources:

  • photovoltaic power plants (PVPP) with an installed capacity of 100 kW to 2 MW including (placement on the roof, perimeter cladding of a building or on land) and
  • other plants using biomass, biogas, landfill gas, sewage treatment plant gas, wind energy, hydropower or geothermal energy with installed capacity from 500 kW up to and including 10 MW.

The only criterion for success in the auction was the bid price, with the call setting a maximum bid price of:

  • 106,80 EUR/MWh for all types of RES except solar and wind energy,
  • 84,98 EUR/MWh for solar and wind energy.

However, the initial enthusiasm of future producers quickly passed, as the Ministry canceled the auction less than 2 months after it was announced. The reason was the epidemiological situation associated with the spread of COVID-19.

Now, however, new information has emerged in the energy market. The state secretary of the Ministry of Economy of the Slovak Republic, Karol Galek, let it be heard at the autumn professional conferences and discussions that the Ministry plans to restart the canceled auction by the end of this year. The conditions of the new auction should copy the conditions of the canceled one, but the installed capacity of the plants should increase from the original 30 MW to 50 MW. However, this information is not officially published at the time of publication of this article.

Of course, this statement stirred up the energy waters again. It can thus be assumed that in the foreseeable future, many producers will not only be able to build some of the renewable sources, but this time (probably) even connect them.

PERMITTING PROCESSES IN CONSTRUCTION

Let's say that the investor will be successful in the auction to build a new source. What processes does it have to go through to put a plant for the production of energy from RES into commercial operation? We start right literally "from the floor", in the area of ​​construction. First of all, it is necessary to resolve the question of where the source will be located.

If the manufacturer wants to build a source on the land (that is, not on the roof of a building, for example), it is important from the view of the whole process for the source to be located on the right land. From a legal point of view, it is not possible to build such a construction on any land, but only on land, on which it is permitted by law.

When choosing the right land, it is necessary to examine two levels - the level of the character of the territory according to the zoning plan of the municipality, in which the source is to be built, and the level of the type of land on, which the source is to be built.

The zoning plan of the municipality addresses the spatial arrangement and functional use of the area. Simply put, it is a kind of "map," in which it is determined where what can be built.

From the point of view of the zoning plan of the municipality, the location of the renewable energy source is possible only in the areas, which are determined in the zoning plan of the relevant municipality from the point of view of the functional area for production, that is, in the production areas. However, if the producer already has the land purchased or leased, and it is not registered in the given zoning plan of the municipality as a production area, there is no need to despair. There is still a possibility to change the zoning plan of the municipality. However, this is a relatively complex process. In addition, not every area can simply be 'changed' into a production area but must meet certain conditions. Moreover, this change must be approved by the authority that approved the original zoning plan.

The second level is the correct choice of the character of the soil of the land. The Building Act clearly stipulates that construction can only be carried out on building land. Building land is the area determined by the zoning plan of the municipality, the zoning plan of the zone, or the zoning decision for construction and the land built-up by the building. However, the Land Register does not recognize the designation 'building land'. Building plots are registered in the Land Register as a "built-up area and courtyard", or as a "other area." According to the Land Register, you can easily see, which land is suitable for construction.

In this context, it is important to note that it is also possible to place a renewable source on agricultural or forest land. These lands are registered in the Land Register as 'arable land', 'hops', 'vineyards', 'orchards', 'gardens', 'permanent grassland' or 'forest land'. However, in order to be able to build on such land, it is necessary to exclude it from the agricultural or forest land fund. From a legal point of view, the exemption represents a change in the type of land. By excluding the land, the type of land changes from for instance "arable land" to "other area".

From the viewpoint of time, the exclusion can be either permanent or only temporary. Agricultural land can be temporarily excluded for a period of 10 years, while for solar power plants the law does allow an extension of the maximum another 10 years. Forest land can be temporarily excluded for a maximum of 20 years. The temporary or permanent exclusion of agricultural and forest land, it is also subject to the obligation to pay a one-time levy to the state. The amount of the levy depends on whether the land is excluded temporarily or permanently, and the creditworthiness of the land excluded is also assessed. The more creditworthy land is being excluded, the more the producer pays. In the case of forest land, the amount of the levy is also based on the locality (for instance for certain districts such as Senec, Šaľa, Galanta, Komárno, the basic amount of the levy increases by up to 50%).

At the end of the period of the temporary exclusion, the producer is obliged to restore the land to its original condition before its exclusion by reclamation measures.

In this context, it should be noted that the aim of the state is to limit the construction of PVPP on agricultural land. This trend is also evidenced by the above-mentioned auction of the Ministry, which stated in the call that the supplement will be provided to PVPP plants with a total installed capacity of 100 kW to 2 MW located on land that is not an agricultural type of land as of the tender date – that is, it is not registered in the Land Register as 'arable land', 'hops', 'vineyards', 'orchards', 'gardens' and 'permanent grassland.' This land thus had to be excluded from the agricultural land fund when the auction was announced. It can be expected that this condition will also be set in the new auction. It is therefore ideal for the future producer of electricity from solar energy to "secure" a suitable plot of land before the next auction is announced.

If the electricity producer has resolved the issues related to the location of the land, it is possible to proceed to the permitting process itself. In this case, it is necessary to go through a zoning proceeding, the result of which is a zoning decision on the location of the construction. Subsequently, the builder proceeds to the construction proceeding, the result of which is the issuance of a building permit. The whole process is completed by the issuance of a building approval decision in the building approval proceeding.

We also draw attention to the possibility for producers to place the PVPP plant not only on land, but also to install it on the roof structure of the building or on its perimeter cladding. In this case, too, the above permitting process must be completed. However, if the source will be used primarily for the production of electricity for the supply to the distribution system (the source will also have an outlet to the distribution system), then a new operation of a production nature is being created here. In this case, it is necessary to proceed with a change in the use of the building before the installation, as the new operation changes and expands the purpose of use of the building compared to the purpose, for which the original building was permitted and subsequently approved.

THE ENVIRONMENT - IMPACT ASSESSMENT ON THE ENVIRONMENT

The second important area that the future producer has to go through is the area of ​​environmental impact assessment (EIA). For some projects, it can be a challenging or even insurmountable obstacle. This is because it is a complex, complicated and lengthy process often with an absolutely uncertain outcome.

The applicable law here is the Act on Environmental Impact Assessment. The future producer will be particularly interested in the Annex no. 8 of this Act, which stipulates, which activities are subject to environmental impact assessment. In the case where the intended activity of the producer is not specified in Annex no. 8, the environmental impact assessment of the source does not have to be completed at all.

For some activities, the EIA must be performed automatically. These are, for example, PVPP plants with an installed capacity of 50 MW or more, hydropower plants of 0,1 MW or more and all wind power plants, regardless of the size of the installed capacity. With these sources, it is assumed that the environmental impact of their activities is so significant that the implementation of an EIA is necessary from the beginning. The whole procedure begins with the elaboration of the plan and ends with the issuance of the final opinion. On average, it is necessary to prepare for a 1 - 2-year procedure.

However, for some other specific activities, the EIA may not have to be automatic. It may be necessary to assess the activity only in a separate procedure other than the EIA. It is an inquiry procedure, or the so-called screening. The purpose of the inquiry procedure is to assess whether or not an EIA is required for a given activity. Thus, it is either a kind of "intermediate step" to the EIA, or a conclusion that the EIA is not necessary. The Annex no. 8 of the Act precisely determines, which activities need to be assessed in that inquiry procedure. Here you will find, for example, PVPP plants with an installed capacity of 5 MW to 50 MW, or hydropower plants up to 0.1 MW. However, PVPP plants with an installed capacity of up to 5 MW are not affected by these processes. 

ENERGY SECTOR - CERTIFICATE FOR THE CONSTRUCTION OF A PLANT

The key document in the field of energy legislation, which must be of interest to the future producer, is the certificate for construction of a plant.

It is a document regulated by Act on Energy, which confirms that the new plant for electricity production will be in compliance with the energy policy of the Slovak Republic and meets the required criteria. For the issuance of the certificate, it is necessary to apply in writing to the Ministry of Economy of the Slovak Republic, and if such a plan is in accordance with the energy policy, the Ministry will issue it within 60-90 days.

In this context, it is important to note that, in addition to basic information such as identification data and the investment plan, the producer must include in his application the opinion of the distribution system operator, to which the plant will be connected. The opinion of the transmission system operator is also required, and if the source has a total installed capacity of more than 1 MW, the producer must also provide the opinion of the RONI. At the same time, for CHE plants, the issuance of a certificate is also carried out in accordance with the Act on Thermal Energy.

However, even in this case, the act specifies the sources, for which the construction of the plant is not conditional on the issuance of a certificate. It is a PVPP plant with a total installed capacity of up to and including 500 kW and, if a different energy source is used than solar energy, up to and including 1 MW.

The validity of the issued certificate is 3 years, while the producer is obliged to inform the Ministry once a year about the progress of the source construction. 

OTHER NECESSARY STEPS

In addition to the above stated processes, future producers will not avoid a lot of other "paperwork" and bureaucracy. This includes not only addressing the issues of project financing or the need to conclude the relevant contractual documentation, but also the final steps, such as obtaining an energy business permit, issuing a pricing decision, performing a functional test and other necessary steps. In this case, it is also necessary to follow the operational rules and other binding documents of individual operators of regional distribution systems, which describe these procedures in detail.

Regardless of all these processes, however, at the end of the day, it is necessary to connect the built source to the distribution system. Legislation stipulates that the distribution system operator shall connect a source to the system if it meets the technical and commercial conditions for the connection of the distribution system operator. However, as we mentioned in the introduction, this is the moment in the whole process, in which producers are currently struggling to succeed.   

WHAT IS THE NEXT?

We can only hope that in the case of the construction and connection of new sources, better times are coming.

Nevertheless, by 2030, Slovakia has committed itself to achieving a share of renewable energy sources in gross final energy consumption of 19.2% (in the year of 2018 we were at 11.89%). This cannot be achieved differently than by deviating from the run-in tracks.


Share the article

More articles by author

View all articles